Progress in Beresford Square
The relocation of underground utility services such as electricity, telecommunications, gas, and mains water footprint is scheduled to be completed by the end of July. These services were within the construction footprint of the station so needed to be moved. Deep services with manholes for wastewater and storm water will complete by August, with the diversion of the 22Kva high voltage cables starting this month and targeted to be complete by September.
We have now commenced the next stage of construction with the start to guide walls which will begin along the western end of the Square. The guide walls provide the layout for the diaphragm walls which are the actual station walls.
The final demolition and heritage salvage of the old Beresford café previously located in the centre of the Square is scheduled to be complete this month.
|