City Rail Link
Videos and Photos.jpg

Milestones-Videos 2017 to 2023

Milestones-Videos 2017 to 2023

Quick links…

 

In this section, in videos we continue our story so far, highlighting some of the major construction highlights and milestones reached.

You can also see our milestones in photos here

Follow us on Facebook, Instagram and Linkedin for regular updates.


CRL Milestones in Videos


2023


September 2023

We sent a drone through the City Rail Link tunnel so you can get the feel of your future train journey underground from the redeveloped Maungawhau Stations to the familiar downtown Waitematā (Britomart).

It's a 3.4km journey.

The first of those two 3.45-kilometre-long tracks for Auckland’s newest railway line – the City Rail Link – has now been laid connecting, underground, Waitematā (Britomart) and Maungawhau Stations. That newly laid track will carry trains south from Waitematā Station (Britomart).


 

July 2023

 

Fenton Street bridge stairs have been successfully installed at the CRLMaungawhau station. This shows the team skilfully lift and shift the 26 tonne stair platform onto the main span of the bridge.

The bridge is expected to open to the public with the opening of Maungawhau station. It will connect Fenton Street and Ngahura Street, enhancing accessibility for people using the station in the future.


July 2023

On 10 July 2023, at the crack of dawn City Rail Link, KiwiRail, Link Alliance and Auckland Transport teams boarded trains to thank customers, and celebrate the return to dual lines running through Maungawhau Station for the first time since July 2020.

The single line enabled Link Alliance to safely undertake demolition and then rebuild the Western Line tracks in a slightly different position to make space for the City Rail Link lines, platform and station building in the area.

 

June 2023

Te Waihorotiu Station's streetscape upgrade programme will regenerate the area with new footpaths, roads, a dedicated cycleway, street furniture and trees. That work is now well underway on Victoria Street West.

 

 

May 2023

The reveal of the Ventilation Building’s façade which has been hiding behind scaffolding for the past year at the Maungawhau site. With the 19-metre-high scaffold removed, artist Graham Tipene’s completed ‘Whakarare’ pattern is strikingly visible on the building’s exterior.

This pattern reflects ‘te ha’ (the breath) as the building will play an important role in housing the ventilation system for the City Rail Link (CRL) tunnels. This ventilation system will work together with equipment at Karanga-a-Hape Station to keep air moving through the tunnels.

Check out the timelapse video showing the installation of the three levels of patterned precast concrete panels, and the black louvres at the top of the building.


March 2023

New Zealand Geographic Board Ngā Pou Taunaha o Aotearoa names railway stations and invited the public to make a submission on proposals for the names of the City Rail Link stations. Their announcement was made on 16 March.

  • Maungawhau (for Mt Eden, an existing station)

  • Karanga-a-Hape Station (for Karangahape, a new station)

  • Te Waihorotiu Station (for Aotea, a new station)

  • Waitematā Station (for Britomart, an existing station).

 

2022


December 2022

We held a contest- and as a result, these were the first kids to ever set foot on a City Rail Link site and also the among the first in the world to walk the entire length of the CRL tunnels underground from Mt Eden.

 


September 2022

The TBM made its final breakthrough at the Te Waihorotiu Station (Aotea) on 14 September 2022.

The Prime Minister visited the CRL construction sites.

The Minister of Transport, Michael Wood, during a visit to CRL's tunnel with the Prime Minister Jacinda Ardern, praised the great progress made



August 2022

Our TBM is on its way to Te Waihorotiu Station (Aotea). Before this final leg of the journey began, we spoke to some of the team who were critical to the TBM’s breakthrough at Karanga-a-Hape Station (Karangahape) and the efforts to relaunch it.

July 2022

Drone footage of the Karanga-a-Hape Station (Karangahape) construction site

May 2022

TVNZ’s Seven Sharp explored our first bored CRL tunnel.

January 2022

The TBM’s front section was transported from the new midtown Auckland CRL Te Wai Horotiu Station (Aotea) back to the Maungawhau Station (Mt Eden) station construction site.

April 2022

The Dame Whina Cooper TBM was launched from 110 metres within a mined tunnel at Maungawhau Station (Mt Eden) on its way to midtown via the Karanga a Hape Station (Karangahape).

 

2021

December 2021

Our Tunnel Boring Machine (TBM) Dame Whina Cooper broke through into Te Wai Horotiu Station (Aotea) marking the end of its epic underground journey from Maungawhau Station (Mt Eden).

September 2021

At Karanga a Hape Station (Karangahape), a breakthrough by our Dame Whina Cooper Tunnel Boring Machine

The Mercury Lane entrance to the new City Rail Link Karanga a Hape Station (Karangahape) is at its deepest point, grade level – 27.5-metres below Mercury Lane. It’s a vast space that will eventually have seven underground levels.

May 2021

The Tunnel Boring Machine was turned on for the first time at the Maungawhau Station (Mt Eden) portal.

 

April 2021

Te Wai Horotiu Station (Aotea) construction moved underground as station manager Matt Sinclair explains progress.

The Chief Post Office (CPO) re-opened resuming its role as the ‘front door’ to Waitematā Station (Britomart).

 

2020

2020 year in review

 

December 2020

Te Komititanga, the striking new people friendly square outside the former Chief Post Office - Waitematā Station (Britomart) -building with the CRL tunnels underneath.

The public were able to see and touch the new CRLTunnel Boring Machine up close at a Boring Day Out event at the Link Alliance Maungawhau Station (Mt Eden) construction site.

Mining starts at the Maungawhau Station (Mt Eden) of the tunnel portal to enable the launch of the Tunnel Boring Machine (TBM).

 

November 2020

The former Chief Post Office has been restored and ready to re-open as Waitematā Station (Britomart) in March 2021.

The big jigsaw puzzle - moving Auckland's heritage Bluestone wall in Albert St began. The wall is in the way of the Albert St tunnels and will be carefully restored in 2023 but moved slightly.

CRL's Ōtāhuhu Station improvements including a new platform were complete.

 

October 2020

The tunnel boring machine is ready to leave its Chinese factory and head for Auckland.

The lower end of Albert Street has been restored and improved with the CRL tunnels underneath.

 

September 2020

The noise enclosure in Mercury Lane is nearing being finished to allow Link Alliance construction workers to work 24 hours a day.

 

June 2020

KiwiRail's staff and contractors worked around the clock during Queen's Birthday weekend around Maungawhau Station (Mt Eden) to install a unique track set called a scissor crossing.

The first quick “blast” at the Link Alliance Maungawhau Station (Mt Eden) construction site. The following week the proper blasts started marking the start of excavations of the two trenches that are initially required for movement of the big tunnel boring machine into the tunnel portal.

A ceremony marked the start of construction for Te Wai Horotiu Station (Aotea).

 

2019

2019 year in review

 

November 2019

Public could walk the tunnels under Lower Queen St.

 

October 2019

CRL-related work included upgrading a section of the Southern Line. KiwiRail installed the first section of a crossover or junction to allow trains to safely switch between the existing main line and a new track being built into Ōtāhuhu station.

 

May 2019

Drone footage of the work continuing at the Chief Post Office - Waitematā Station (Britomart)- and Lower Queen Street.

 

January 2019

Over the Christmas period, work was done around the Strand railway yard in Parnell. The rail works include introducing a new track cross-over point that allows trains to more easily access the existing Strand station and stabling facility, along with some track realignment.

 

May 2019

Micro-sized tunnel boring machine Jeffie completed her underground journey below Mt Eden as part of the Maungawhau Station (Mt Eden) site project. Jeffie was used to build a new, 423-metre-long stormwater main 17 metres below city streets. The existing main between Water and Nikau Streets would have been in the way of the tunnels.

 

2018

December 2018

We took the opportunity of making the Lower Queen Street area a fun public place before further construction took place.

 

November 2018

A major engineering feat achieved. The heritage Chief Post Office - Waitematā Station (Britomart)- had to be lifted to enable the tunnels to be built underneath.

 

July 2018

Work continues in the lower end of Albert Street.

 

2017

August 2017

A time-lapse showing work at the corner of Albert and Customs Sts.

Work progresses in Victoria and Albert Streets

 

July 2017

Construction work for tunnels down the lower end of Albert Street

Then CRL CEO (Chris Meale) surveys the construction work underway downtown near the Chief Post Office- Waitematā Station (Britomart).

 

June 2017

The cut and cover tunnel construction process in Albert St was underway

Then transport minister (Simon Bridges) and Auckland Mayor (Len Brown) sign documents to give CRL the green light.

 

May 2017

Work underway inside Waitematā Station (Britomart).

 

January 2017

A temporary Waitematā Station (Britomart) entrance opened so work could start on building the tunnels under the CPO