Kia ora neighbours,
In this update we will provide you with the latest construction news from Beresford Square, Mercury Lane and the mined tunnels; in addition an update on the progress of the Tunnel Boring Machine (TBM).
You can view its progress on the online TBM tracker via www.digcrl.co.nz
Excavation continues at both Mercury Lane and Beresford Square. We are currently constructing level B2 at both entrances.
This ‘top down’ construction finishes this July at B2 for Mercury Lane and will continue to B4 for Beresford Square. Below these levels the team excavate to the deepest floor B7, with the methodology then changing to ‘bottom up’ construction.
At 32 metres underground, Karangahape will be the deepest of CRL’s stations, with entrances on both Mercury Lane and Beresford Square.
|